The Journey Through the Building Process

Overall Job Completion

  • Overall Completion 80% 80%

Address

Fink, Thomas & Jennifer
Cedar Road
Mishawaka, IN 46545

Pre-construction Phase

  • First Visit 100% 100%
  • Site Visit 100% 100%
  • Sales 100% 100%
  • Workbooks Created 100% 100%
  • Health Permit (Septic and Well Permits) 100% 100%
  • Building Permit 100% 100%
  • Construction Preview 100% 100%

Utilities

  • Electric Application 100% 100%
  • Electrical Engineering Meeting 100% 100%
  • Natural Gas or Propane Application 100% 100%
  • Natural Gas Engineering Meeting 100% 100%

Construction Phase

  • Workbooks Review 100% 100%
  • Escavation (Hole Dug) 100% 100%
  • Footers Poured 100% 100%
  • Foundation Poured (Walls) 100% 100%
  • Foundation Floor Poured (Garages and Basements Only) 100% 100%
  • Sill Plates Installed 100% 100%
  • Partial Back Fill 100% 100%
  • Egress Windows and Jackposts Ordered 100% 100%
  • House Set 100% 100%
  • Garage Build 100% 100%
  • Electrical Installed 100% 100%
  • Gas Installed 100% 100%
  • HVAC Installed 100% 100%
  • Plumbing Finished 100% 100%
  • Gutters Installed 100% 100%
  • Flatwork (Sidewalks, Porch Caps, and/or Driveway) 100% 100%

Fit & Finish

  • Marriage Line 100% 100%
  • Drywall Repairs 100% 100%
  • Fit & Finish 90% 90%

Aftermarket

  • 6 Months 0% 0%
  • 1 Year 0% 0%

Certificate of Occupancy

  • Electrical Inspection 100% 100%
  • Mechanical Inspection 100% 100%
  • Plumbing Inspection 100% 100%
  • Final Inspection 90% 90%

Notes

Update 10/3/2023

Mark is to go next week to handle the bookshelves and tower. Will need to get Toliver there to complete the list of items that Fink’s and Adam have discussed.

Been A While

I apologize for the lateness of this update. We have been talking in person about all of this.

First and foremost, we are working on getting all the water out of the crawl from the unseasonable rain we received. The garage floor was poured and is in. Last week the garage apron and the sidewalks were prepped and poured on Friday. With all of the rain that came in on Sunday and Monday of this week, we are now in a holding pattern to get the driveway created. Currently, the plan is to have the backyard scathed and moved to create the driveway on August 24th, with the gravel delivered a couple of days later.

The porch and garage have been inspected and have passed.

Fit and finish is started and will move to final fit and finish very soon.

First Post and Update!

Hello, and welcome to the first post and update of your build log! Today we created the build log, which shows you where we are in the process. Included are some key features of your site, including the process you are at in the system, photos of your build and property, and a map of where your house is located! If you have questions or comments, please do not hesitate to reach out to us via the form, and we will get back to you within 48 hours of filling it out.